Short answer: building a house in Kenya costs about KES 40,000 to KES 110,000 per square metre in 2026. A typical 3-bedroom bungalow costs around KES 5M–KES 9.8M at standard finishes. The actual price depends on the design, finishes, soil and location, so use the calculator below for a first estimate, then get a BQ for a firm figure.
Construction cost per square metre in Kenya
| Finish level | Cost per m² | What it means |
|---|---|---|
| Economy finish | KES 40,000 – KES 50,000 | Simple design, local materials, basic fittings. |
| Standard finish | KES 50,000 – KES 70,000 | Typical family home: tiled floors, good fittings, gypsum ceilings. |
| Premium finish | KES 70,000 – KES 110,000 | Architect-led design, imported finishes, large spans and glazing. |
Cost of building a bungalow or maisonette
Typical floor areas and total build cost (structure and finishes, excluding land) at each finish level.
| House type | Typical size | Economy finish | Standard finish | Premium finish |
|---|---|---|---|---|
| 2-bedroom bungalow | 70–90 m² | KES 2.8M – KES 4.5M | KES 3.5M – KES 6.3M | KES 4.9M – KES 9.9M |
| 3-bedroom bungalow | 100–140 m² | KES 4M – KES 7M | KES 5M – KES 9.8M | KES 7M – KES 15.4M |
| 4-bedroom bungalow | 150–190 m² | KES 6M – KES 9.5M | KES 7.5M – KES 13.3M | KES 10.5M – KES 20.9M |
| 3-bedroom maisonette | 140–180 m² | KES 5.6M – KES 9M | KES 7M – KES 12.6M | KES 9.8M – KES 19.8M |
| 4-bedroom maisonette | 180–250 m² | KES 7.2M – KES 12.5M | KES 9M – KES 17.5M | KES 12.6M – KES 27.5M |
| 5-bedroom maisonette or villa | 250–350 m² | KES 10M – KES 17.5M | KES 12.5M – KES 24.5M | KES 17.5M – KES 38.5M |
House construction cost calculator
Estimated build cost: –
Indicative only. Excludes land, fees, approvals and external works. Ask for a BQ for a firm price.
Where the money goes
On a typical house the budget splits roughly like this. Knowing the split helps you plan stage payments and spot an unbalanced quote.
- Substructure (10–20%): excavation, foundation and ground slab. Higher on black cotton soil or sloping plots.
- Superstructure (25–35%): walling, columns, beams and upper floor slabs.
- Roofing (10–15%): trusses, roofing sheets or tiles, gutters.
- Finishes (20–35%): plaster, flooring, ceilings, paint, doors and windows, kitchen and wardrobes.
- Services (10–15%): plumbing, electrical, water tanks, septic tank or sewer connection.
Costs people forget
- Architect, engineer and quantity surveyor fees, usually 8–15% of the build cost.
- County approval fees, the NCA levy (0.5% of the contract value on projects above KES 5 million) and NEMA where required.
- Soil test, site survey, water and power connections.
- Boundary wall, gate, paving and landscaping.
- A contingency of about 10% for price changes and decisions made on site.
How to keep the cost down without cutting corners
- Keep the plan simple: rectangular shapes with fewer corners use less material and labour.
- Get a BQ before you start, and compare contractors on the same BQ.
- Use local walling stone and standard door and window sizes.
- Do not save on the foundation, structure or waterproofing; those are the expensive things to fix later.
- Make design decisions before work starts; changes on site are the biggest cause of overruns.
Cost by region
Rates are similar across Kenya, with some differences. Nairobi and its satellite towns (Ruiru and Kiambu, Kitengela, Syokimau) have the most competitive material supply. The Coast needs corrosion-resistant materials, and remote rural sites add transport costs. Black cotton soil adds to the foundation cost wherever it occurs.
Rates are indicative as of November 2026, based on our own BQs and published industry figures for 2025–26, and will move with material prices. They are not a quotation. Before you build, also read our building approvals guide.
Frequently asked questions
Between about KES 40,000 and KES 110,000 per square metre of floor area, as of November 2026. A standard-finish family home usually costs KES 50,000–KES 70,000 per m².
A 3-bedroom bungalow of 100–140 m² costs roughly KES 4M to KES 15.4M, and about KES 5M–KES 9.8M at standard finishes.
A 4-bedroom maisonette of 180–250 m² costs roughly KES 9M to KES 17.5M at standard finishes.
Building is usually cheaper per square metre than buying a finished house in the same area, provided the cost is controlled with a proper BQ and supervision.
Land, professional fees (about 8–15%), approvals and NCA levy, soil tests, external works such as boundary walls, paving and boreholes, and VAT where it applies.
Kwa wastani ni kati ya KES 40,000 na KES 110,000 kwa kila mita mraba, kutegemea ubora wa finishes, aina ya udongo na ramani ya nyumba. Tupigie kwa BQ ya bure.