Short answer: to build legally in Kenya you need county-approved architectural and structural drawings, an NCA-registered contractor with the project registered with the NCA, and for bigger projects a NEMA licence. At the end you need an occupancy certificate. Here is the process step by step.
The building approval process in Kenya
- 1
Check the land first
Do a title search, confirm the beacons with a surveyor, and check the zoning for your area: plot coverage, number of floors and permitted use. This decides what you are allowed to build before you pay for drawings.
- 2
Prepare the drawings
Architectural drawings by a BORAQS-registered architect and structural drawings and calculations by an EBK-registered engineer, plus a site plan. Larger projects may also need a soil test, drainage plan and fire plan.
- 3
Submit to the county
Plans go to the county government for approval, with your title or lease, ID, rates clearance and the approval fee (worked out from the size or value of the project). Nairobi uses an online e-development permit system; other counties use online portals or their planning office.
- 4
NEMA, where required
Bigger developments such as apartments, commercial buildings and roads usually need an Environmental Impact Assessment licence from NEMA, prepared by a registered EIA expert. Many single family homes do not; your consultant will confirm.
- 5
Register the project with the NCA
Construction works must be done by an NCA-registered contractor, and the project registered with the National Construction Authority before work starts. A levy of 0.5% of the contract value applies to projects above KES 5 million.
- 6
Build, with inspections
County inspectors may visit at key stages (setting out, foundation, structure). Keep the approved drawings on site and build to them; changes need fresh approval.
- 7
Occupation certificate
At completion, apply for the certificate of occupation (occupancy certificate) before moving in or letting the building, and connect water, sewer and power.
Documents you will usually need
- Title deed or lease, and ID or company registration documents
- Architectural drawings and site plan (registered architect)
- Structural drawings and calculations (registered engineer)
- Current land rates clearance
- EIA licence where required, and other reports your county asks for
Requirements and fees differ between counties and change over time, so confirm with your county planning office or let us handle it. For what the build itself will cost, see our 2026 building cost guide.
Frequently asked questions
Usually from a few weeks to about three months, depending on the county, the size of the project and whether the submission is complete. Complete, well-prepared drawings are the biggest factor.
Yes. Every permanent building in Kenya needs approved plans from the county government, even on your own land and even for a single family home.
Not always. Many single dwellings do not need a full EIA licence, but apartments, estates and commercial buildings usually do. Check with a registered EIA expert before you start.
The county can stop the works, fine you or order the building demolished, and you may struggle to get an occupancy certificate, a mortgage or a buyer later.
Yes. We prepare the drawings, submit to the county, follow up the approval, and handle NCA registration and NEMA where required.